The Schedule's Main page contains the basic information for your schedule.
The following fields summarize the content of the schedule. The Schedule document needs to be in edit mode before you can modify the fields. Schedule attributes are grouped under the following sections:
Indicates the current state
of the schedule.
Displays the title of the schedule. You can change the title in the
Details section.
A string of characters that uniquely identifies the schedule document
within the workspace. You can edit the number in the Details
section.
Displays the date that work on the schedule should start. You can change
the start date in the Details section.
Displays the date that work on the schedule should finish. You can change
the finish date in the Details section.
The Project section displays a simplified version of the information available on the Projects tab. Use this section to quickly view a list of projects currently linked to the document, and to create, read and delete project links in edit mode. Information displayed in the project section is also available on the Projects tab, and any changes you make in the Project section is synchronized with the Projects tab.
|
Note:
|
Using the Project section, you can set the current document's project linking status to:
Select to remove all project links for the current document. You can only remove project links if you have the appropriate role security permissions, and your contact document has a link to the same projects.
Select to display a box where you can enter a single project link for the current document. Click the Magnifying Glass icon
Select to display a box where you can enter multiple project links for the current document. Click the Magnifying Glass icon
Select to link the current document to all projects within the current workspace.
The current status of project linking is displayed in the section header so that you can quickly scan project status with all the sections on the Main page collapsed. The document must be in edit mode before you can update information in the Project section.
Click
Select the calendar to use for calculating the schedule. If no calendar
is selected, the predefined calendar is used.
Type the estimated total number of hours needed to complete tasks in
the schedule. This field is for information purposes only and is not affected
by any values from the Gantt.
Type the date that work on the schedule should finish. The Finish
Date field is required. Once the schedule is saved, this date is
updated by the dates in the Gantt and cannot be updated in the Schedule
document.
Click
Type a string of characters that uniquely identifies this schedule,
or leave it blank if Proliance is configured to supply one. You can configure
the format of this number by using Proliance
Local Admin. For details, refer to "Editing the Number Format"
in the Proliance Local Admin on-line help.
Click
Type the date that work on the schedule should start. The Start
Date field is required. Once the schedule is saved, this
date is updated by the dates in the Gantt and cannot be updated in the
Schedule document.
Type the title of the schedule. The Title
field is required.
This option handles how the CPM Gantt distributes work on linked tasks
that are overlapping in the schedule. Select Retain
Logic toensure that any remaining work on the task still follows precedence logic. Select Progress Override to ensure that work, once started, is completed and unaffected by any precedence logic.
Select this option to calculate the critical path from the start date
or finish date of the schedule.
Select Single to calculate
one critical path. Select Multiple
to calculate multiple critical paths.
With this option set to Single, only the one overall critical path whose finish date affects the finish date of the schedule is displayed. Modifying the finish date of any of the secondary critical paths may not impact the overall finish date of the schedule.
With this option set to Multiple, the CPM sets the late finish date of all the planning objects that do not have successors and constraints to the early finish dates, making them critical.
Select the currency for the schedule costs.
Use this with the Use Default Hours
Per Day check box. The value is set to 8.
Indicate whether it is a "Regular" or "Template"
schedule. A Template schedule is one that can be used as a template to
create other regular schedules. When you categorize a schedule as either
a regular or a template schedule, you can also use filters to view schedules
that fall under either category.
Select this check box to show the time in the date fields. Leave this
check box clear if you do not want the time to show in the date fields.
Select this check box to use a default value for the hours per day.
The default is 8 hours.
The WBS (Work Breakdown Structure) Codes section allows you to activate and preview WBS lookups for applying a WBS to your schedule. For more information, see "About WBS Codes".
Displays the actual work performed in hours, based on the total number
of actual work hours in the schedule.
Displays the total percent complete for all the tasks in the Gantt.
Displays the estimated finish date for the schedule, based on the dates
in the schedule.

Displays the duration that is calculated as
Duration = Estimated Finish - Completed Date
without regard to work hours assigned to each working day.
Displays the estimated start date for the schedule, based on the dates
in the Gantt chart.
Displays the remaining work in hours, based on the total number of remaining
work hours in the schedule.
Click this button to open the Collaborative Gantt. This button is available only after you save the document.
Click this button to view the CPM Gantt. This button is available only after you save the document.
For more information about the actions available on this page, refer to "Schedule Workflow States".
Summary