The Schedule's Main page contains the basic information for your schedule.
The following fields summarize the content of the schedule. The Schedule document needs to be in edit mode before you can modify the fields. Schedule attributes are grouped under the following sections:
The Project section displays a simplified version of the information available on the Projects tab. Use this section to quickly view a list of projects currently linked to the document, and to create, read and delete project links in edit mode. Information displayed in the project section is also available on the Projects tab, and any changes you make in the Project section is synchronized with the Projects tab.
Note:
|
Using the Project section, you can set the current document's project linking status to:
The current status of project linking is displayed in the section header so that you can quickly scan project status with all the sections on the Main page collapsed. The document must be in edit mode before you can update information in the Project section.
With this option set to Single, only the one overall critical path whose finish date affects the finish date of the schedule is displayed. Modifying the finish date of any of the secondary critical paths may not impact the overall finish date of the schedule.
With this option set to Multiple, the CPM sets the late finish date of all the planning objects that do not have successors and constraints to the early finish dates, making them critical.
The WBS (Work Breakdown Structure) Codes section allows you to activate and preview WBS lookups for applying a WBS to your schedule. For more information, see "About WBS Codes".
Displays the duration that is calculated as
Duration = Estimated Finish - Completed Date
without regard to work hours assigned to each working day.
For more information about the actions available on this page, refer to "Schedule Workflow States".