Open topic with left hand navigation
Completing a Drawing/Submittal Package
When a package
has finished its review
process, it is returned to the managing contact or someone with equivalent
authority. He or she then reviews all the reviewers' recommendations and
then sets a final state
for each drawing / submittal
document in the package:
- Accepted:
The revision of the document is accepted for construction.
Note: When a revision of a document is accepted, Proliance
will automatically change the state of any previously accepted revision
of the same item from Accepted
to the standard Canceled state. The canceled reason
for that revision will be set to Superceded.
- Rejected: The revision of the document is not acceptable for construction.
- Canceled: The revision of the document is no longer applicable.
Completing a package also sets its state
to Complete, regardless of the
recommendations for each document in the package.
Rejected Documents
If the managing contact completes a package containing rejected
documents, Proliance automatically creates a new revision of the package
containing revisions of the rejected documents in Draft
state. For more information, see "Creating
a Drawing/Submittal Package Revision".
If the managing contact rejects all
the documents in the package and then completes the package, that package
is considered "rejected" and the Rejection
Date is automatically added to the More
Details section of the Main
page.
To
complete a package
-
for the type of package that you are creating.
- Select the package
to complete.
- Click the Drawings/Submittals page and review the recommendations.
- Click Edit.
- Under Change
Status on Completion, select a final
workflow state for each item. Each drawing/submittal may have a different list of states from which to choose. Each list contains all the document's states (including the custom states) that were created from an Accepted, Rejected or Cancelled state type.
- Click Complete.