Splitting Resource Assignments

If necessary, you can interrupt the work on an assignment. You can split the assignment and move the remaining part of the work to a later date.

Your security role must have permission to edit resource assignments.  For more information, see "Permissions for Scheduling".

To split an assignment

  1. Ensure that the assignments are displayed by clicking the Show/Hide Assignments button. This button should be pressed down to display the assignments.
  2. Click Split Assignment.
  3. Point to the assignment bar.
  4. The portion you want to move turns an orange-red color.
  5. Drag the remaining portion of the assignment to the date you want work to resume.
  6. The Gantt displays the two portions of the split task are connected by light line.

  7. To split another assignment, click Split Assignment and follow this procedure again.