About Invoice Line Item Recalculation
Whenever you edit
an invoice line item, Proliance performs tests to determine whether or
not your edit makes it necessary to update other values in the line item.
If your edits make an update necessary, Proliance
performs a series of calculations that enable it to update all of the
line item's values. This includes values that may not currently be visible
on the Line
Items page because of the current view.
To ensure consistent results, Proliance always
performs the tests and calculations in the same order before each update.
Proliance performs three tests:
Test One: Does the To Date Total Progress exceed
the absolute value of the Scheduled
Amt?
- If "no,"
Proliance proceeds to Test Two.
- If "yes,"
Proliance notifies you, then undoes the edits to the line item.
For a Scheduled Amount
greater than zero, the To Date Total
Progress must be equal to or less than the Scheduled
Amt.
For a Scheduled Amount
less than zero, the To Date Total
Progress Amt must be equal to or greater than the Scheduled Amount. For
example, if the Scheduled Amount
= -10, then the To Date Total Progress
can be -10 or greater. Proliance would accept a To
Date Total Progress value of -5, but not -11.
Test Two: Does To Date Progress Amt exceed the
Scheduled
Amt?
- If "no",
Proliance proceeds to Test Three.
- If "yes,"
refer to the following table:
Note that if you are using Uncontrolled Total billing,
there are no restrictions on the To
Date Progress Amt exceeding the Scheduled
Amt.
Test Three: Do the edits to the line item result in
a To
Date Progress Amount that has a different sign (+/-) than the
Scheduled
Amt?
- If "no",
Proliance updates the values in each column of the line item.
- If "yes,"
Proliance notifies you, then undoes the edits to the line item.
Once you successfully edit part
of a line item, Proliance automatically updates the rest of the line items,
in the order listed below.
"General"
columns
- This Invoice General
Pct = Total To Date Invoiced Amt / Scheduled Amount
- This Invoice General
Qty = Total To Date Invoiced Amt / Scheduled Amount * Scheduled Qty
- This Invoice General
Sub Amt = Total To Date Invoiced Amt - This Invoice General Sub Material
Amt
- To Date Progress
General Amt = Previous General Amt + Total To Date Invoiced Amt
- To Date Progress
General Pct = To Date Progress General Amt / Scheduled Amount
- To Date Progress
General Qty = To Date Progress General Amt / Scheduled Amount * Scheduled
Qty
- This Invoice Retainage
General Amt (if using the This Invoice
Method):
This Invoice Retainage General Amt = Total To Date
Invoiced Amt * This Invoice Retainage General Pct
This Invoice Retainage General Amt = To Date Retainage
General Pct * To Date Progress General Amt - Previous Retainage General
Amt
"Stored"
columns
- This Invoice Stored Pct = This
Invoice Stored Amt / Scheduled Amount
- This Invoice Stored Qty = This
Invoice Stored Amt / Scheduled Amount * Scheduled Qty
- To Date Progress
Stored Amt = Previous Stored Amt + This Invoice Stored Amt
- To Date Progress
Stored Pct = To Date Progress Stored Amt / Scheduled Amount
- To Date Progress
Stored Qty = To Date Progress Stored Amt / Scheduled Amount * Scheduled
Qty
- This Invoice Retainage
Stored Amt (if using the This Invoice
method):
This Invoice Retainage Stored Amt = This Invoice
Stored Amt * This Invoice Retainage Stored Pct
This Invoice Retainage Stored Amt = To Date Retainage
Stored Pct * To Date Progress Stored Amt - Previous Retainage Stored Amt
"Total"
columns
- This Invoice Total Amt = Total
To Date Invoiced Amt + This Invoice Stored Amt
- This Invoice Total Pct = This
Invoice Total Amt / Scheduled Amount
- This Invoice Total Qty = This
Invoice General Qty + This Invoice Stored Qty
- To Date Progress
Total Amt = To Date Progress General Amt + To Date Progress Stored Amt
- To Date Progress
Total Pct = To Date Progress Total Amt / Scheduled Amount
- To Date Progress
Total Qty = To Date Progress General Qty + To Date Progress Stored Qty
- Previous Progress
Total Amt = Previous Progress General Amt + Previous Progress Stored Amt
- Previous Progress
Total Qty = Previous Progress General Qty + Previous Progress Stored Qty
Other
"Retainage" columns
- To Date Retainage
General Amt = This Invoice Retainage General Amt + Previous Retainage
General Amt
- To Date Retainage
General Pct (if using the This Invoice
method):
To Date Retainage General Pct = To Date Retainage
General Amt / To Date Progress General Amt
- This Invoice Retainage
General Pct (if using the To Date method)
This Invoice Retainage General Pct = This Invoice
Retainage General Amt / Total To Date Invoiced Amt
- To Date Retainage
Stored Amt = This Invoice Retainage Stored Amt + Previous Retainage Stored
Amt
- To Date Retainage
Stored Pct (if using the This Invoice
method):
To Date Retainage Stored Pct = To Date Retainage
Stored Amt / To Date Stored Amt.
- This Invoice Retainage
Stored Pct (if using the To Date method):
This Invoice Retainage Stored Pct = This Invoice
Retainage Stored Amt / This Invoice Stored Amt
- This Invoice Retainage
Total Amt = This Invoice Retainage General Amt + This Invoice Retainage
Stored Amt
- Previous Retainage
Total Amt = Previous Retainage General Amt + Previous Retainage Stored
Amt
- To Date Retainage
Total Amt = To Date Retainage General Amt + To Date Retainage Stored Amt
- To Date Retainage
Total Pct = To Date Retainage Total Amt / To Date Progress Total Amt
- This Invoice Retainage
Total Pct = This Invoice Retainage Total Amt / This Invoice Total Amt
"Net
Payable" and "Balance Due" columns
- This Invoice Net
Payable Amt = This Invoice Total Amt - This Invoice Retainage Total Amt
- This Invoice Balance
Due Amt = Scheduled Amount - To Date Progress Total Amt