Setting the Text to Left/Right of Gantt Bars Options
For summaries, milestones, and tasks, you can customize the
text that is displayed on the right and left sides of the bars in the
Gantt chart.
To
customize the text
- Open
the Options
dialog box.
- Click
the Gantt tab.
- Locate
the Text to the Left/Right of Task Bar
section.
- Under
Summary,
Milestone, Task,
or Assignment, select the value
that you want to appear on the left side and the ride side of the bar
in the Gantt chart.
- Click
OK.