Use this option to display or hide the slack lines between planning objects. Slack is the amount of time that a planning object can slip before it affects another planning object or the workspace finish date. The slack lines are displayed in the Gantt chart to display positive or negative slack. Negative slack is displayed in red to the left of the task bar and indicates that the planning object has slipped too far and affects the successor task. Positive slack is displayed in blue to the left of the task bar and indicates that time can pass between two linked planning objects.
Slack dates are calculated in the CPM Gantt.