Setting the Percent Complete Calculation Type

The Percent Complete field contains the percentage value of the task completion. You can enter the percent complete yourself or Proliance can calculate it for you.

When a task is first created, the percent complete is zero percent. As soon as you enter values for the actual duration, remaining duration, or actual work, Proliance calculates the percent complete. The percent complete can be calculated by work, by duration, or by standard.

If the Percent Complete field is set to a value greater than zero and you have not yet entered an actual start date, the Actual Start field is set to the scheduled start date. If the Percent Complete field is set to 100, the Actual Finish field is set to the scheduled finish date.  

ClosedTo change calculating the percent complete

  1. Open the Options dialog box.
  2. Click the Common tab.
  3. Under Percent Complete Calculation Type, select one of the following:
  4. Click OK.

Note:

  • When the "No Work" check box is selected for an assignment, the Percent Complete Calculation Type does not use Work when calculating the percent complete.