Cost and Fixed Cost Resource Assignments

For each task, the assignment as "Cost Only" or as "Fixed Cost". Select these options depending on your tracking needs. Note that these options can only be set at the assignment level.

Cost Only

Use the "Cost Only" option to report on cost without tracking work performed on assignments. Once this option is selected, the work hours for an assignment are set to zero and only cost values are calculated for the resource. Cost Only values can only be spread linearly over the duration of the task. Adjustments to the remaining duration of a task or assignment forces a recalculation of the Cost Only value for a task. As an example, the Cost Only option can be used when material resources are assigned to tasks.

Fixed Cost

Use the "Fixed Cost" option to disable the recalculation of the Cost Only values when the duration of the assignment or the task is updated. This option is useful for tracking income or a lump sum value. Regardless of the duration of the task, the Cost Only values remain fixed, unless you modifies the value. This option also disables automatically recalculating the percent complete and remaining duration.

Once you select this option, ensure that both the actual and remaining values at the assignment level for each task are set to Fixed Cost. If you do not modify the remaining value after entering an actual total cost, the total cost for the assignment is displayed as a positive actual remaining value.

Combinations

The following describes the options with different combinations of Cost Only and Fixed Cost resource Assignments:

To set the Cost Only and Fixed Cost options

  1. Open the Gantt.
  2. Select the planning object with a resource assignment.
  3. Right-click and select Properties.
  4. The Properties dialog box appears.

  5. Select the Expenses tab and select the "Cost Only" and "Fixed Cost" options appropriately.

Note: The Cost and Fixed Cost options are only available on tasks that have resources assigned to them.

  1. Click Close.