Removing Approved Schedules

Use the procedure below to remove an approved schedule from a schedule or a planning object. If you remove approval for a summary, all the planning objects in that summary also have their approval removed.

Your security role must have permission to work with approving schedules and planning objects.  For more information, see "Permissions for Scheduling".

To remove an approved schedule

  1. Open the Gantt.
  2. Right-click the schedule or planning object for which you want to remove the approved schedule, and select Remove Approved.
  3. Proliance removes the approved schedule for the schedule or planning object.