            Planning Objects - Schedule Tab
        The planning object's 
 Schedule tab contains the basic schedule information for your planning 
 object.
        The following fields summarize the content of the Schedule tab. 
 The fields may be displayed as read-only or editable based on the type 
 of planning object you are viewing.
         Header 
 Section
Header 
 Section
        
        
            
                - Name: Type the name of your planning object. Type the name of your planning object.
- Responsible 
 Person: Select the name of the resource responsible for the planning object. 
 This field only denotes the resource that is ultimately responsible for 
 the work and is not the same as assigning one or more resource(s) to the 
 planning object. Note that the people displayed in the responsible person 
 list are taken from the Contacts, not the Resources. This field defaults 
 to the currently logged on user. Select the name of the resource responsible for the planning object. 
 This field only denotes the resource that is ultimately responsible for 
 the work and is not the same as assigning one or more resource(s) to the 
 planning object. Note that the people displayed in the responsible person 
 list are taken from the Contacts, not the Resources. This field defaults 
 to the currently logged on user.
- Linked Activity: Select an activity to be linked to the planning object. Select an activity to be linked to the planning object.
- Status: Indicates the status of a planning object. You can change the status 
 by changing the start date. Indicates the status of a planning object. You can change the status 
 by changing the start date.
 
         Schedule
Schedule
        
        
            
                - Actual Duration 
 (Days): Type the number of days already spent on the task. Type the number of days already spent on the task.
- Actual Duration 
 (Hours): Type the number of hours already spent working on the task. Type the number of hours already spent working on the task.
- Actual Work: Displays the number of hours already spent working on the task for all 
 resources assigned to the task. Displays the number of hours already spent working on the task for all 
 resources assigned to the task.
- No Work: Select this check box if you do not want to track work for an assignment. 
 Selecting this check box disables the Actual Work, Remaining Work, and 
 Total Work fields. This check box is only available for assignments. Select this check box if you do not want to track work for an assignment. 
 Selecting this check box disables the Actual Work, Remaining Work, and 
 Total Work fields. This check box is only available for assignments.
- Remaining 
 Duration (Days): Type the remaining number of days that can be spent working on the task. Type the remaining number of days that can be spent working on the task.
- Remaining 
 Duration (Hours): Type the remaining hours that can be spent working on the task. Type the remaining hours that can be spent working on the task.
- Remaining 
 Work: Displays the remaining number of hours that can be spent working on 
 the task for all resources assigned to the task. Displays the remaining number of hours that can be spent working on 
 the task for all resources assigned to the task.
- Total Duration 
 (Days): Type the total number of days that can be spent working on the task. Type the total number of days that can be spent working on the task.
- Total Duration 
 (Hours): Type the total number of hours that can be spent working on the task. Type the total number of hours that can be spent working on the task.
- Total Work: Displays the total number of hours that can be spent working on the 
 task for all resources assigned to the task. Displays the total number of hours that can be spent working on the 
 task for all resources assigned to the task.
 
         Dates
Dates
        
        
            
                - Actual Start: Select the date that the planning object started. Select the date that the planning object started.
- Actual Finish: Select the date the planning object finished on. Selecting this date 
 fills in the Percent (%) Complete field and Completed box. Select the date the planning object finished on. Selecting this date 
 fills in the Percent (%) Complete field and Completed box.
- Remaining Start: Select the date that the remaining work on the planning object should 
 continue on. Select the date that the remaining work on the planning object should 
 continue on.
- Remaining Finish: Select the date that the remaining work on the planning object should 
 finish. Select the date that the remaining work on the planning object should 
 finish.
 
         Progress
Progress
        
        
            
                - Started: Select the check box to indicate that work on the planning object has 
 started. This check box is automatically selected if you add work against 
 the object or select a date in the Actual Start field. Select the check box to indicate that work on the planning object has 
 started. This check box is automatically selected if you add work against 
 the object or select a date in the Actual Start field.
- Complete: Select the box to indicate that work on the planning object has finished. 
 This box is also selected if you enter an Actual Finish Date or set the 
 Percent (%) Complete to 100%. Select the box to indicate that work on the planning object has finished. 
 This box is also selected if you enter an Actual Finish Date or set the 
 Percent (%) Complete to 100%.
- Percent (%) Complete: Type the percentage of work done on the task. If you type 100%, the 
 Completed box is selected and the Actual Finish is added. Type the percentage of work done on the task. If you type 100%, the 
 Completed box is selected and the Actual Finish is added.