About Contract Billing Rules

A contract's billing rules determine whether you can over-bill line items on invoices against the contract. Proliance has three contract billing rules: Controlled Total, Uncontrolled Total, and Variable Total. A contract must always adhere to one of the three billing rules. Note that auto-commit contracts can only use Controlled Total billing rules.

ClosedExamples

The following table defines and compares the three contract billing rules:

  Controlled Total Uncontrolled Total Variable Total

Over-billing on invoice line items permitted

No

Yes

Yes

Contract value changes after line item over-billing

No

Yes

Committed costs increase after over-billing

No

Yes

Can edit the Scheduled Amt and Scheduled Qty on any invoice

No

No

No; only possible on a new invoice