Swapping a Resource Assignment

If necessary, you can interrupt the work done by one resource and assign the remaining work to another resource.

Your security role must have permission to edit resource assignments.  For more information, see "Permissions for Scheduling".

To swap a resource assignment

  1. Right-click the task that you wish to change the resource assignment for, and select Add/Edit Resource Assignment.
  2. The Add/Edit Resource Assignment dialog box appears.

  3. Select the resource to be replaced in Assigned Resources, and the replacement resource in Resource List.  
  4. Click the Swap <> button.
  5. Proliance assigns the remaining part of the work to the replacement resource. The part of work that was done by the replaced resource is marked as completed.