Open topic with left hand navigation
Setting the Schedule Behavior
Use the schedule behavior options to determine the behavior
of completed tasks and for task constraints.
To
set the schedule behavior
- Open
the Options
dialog box.
- Click
the Common tab.
- Under
Schedule Behavior,
set the following options:
- Set Complete Flag Removes Remaining Part of Work:Select this option to indicate that once the Completed check box is
selected in the task, the remaining part of work needs to be set to zero.
If this option is not selected, when the Completed check box in the task
is selected, remaining work on task becomes the actual work.
- Finish Constraint Resolving Allows Task Start Moving:If a task's duration increases, this increase may conflict with the
task constraint. Select this check box to allow the task's start date
to be rescheduled to keep within the constraint. If the check box is not
selected, the task duration is cut.
- Click
OK.