            Setting Gantt Preferences
        You can customize your Gantt chart using the following preferences. 
 For more information, see "About 
 Gantt Preferences".
        To 
 customize your Gantt preferences
        
            - Open the Edit 
 Gantt Preferences dialog box.
- Use the following 
 options to customize your Gantt view:
                - Set Assignment Name Label: Specify the contents of the resource assignment label 
 by selecting Show Resource Name 
 for the name of the resource and Show 
 Contact Name for a resource that has a contact associated with 
 it. This is the label that appears to the left or right of the bar in 
 the gantt chart. Specify the contents of the resource assignment label 
 by selecting Show Resource Name 
 for the name of the resource and Show 
 Contact Name for a resource that has a contact associated with 
 it. This is the label that appears to the left or right of the bar in 
 the gantt chart.
- Gantt Settings: Select the "Use Prefiltering" check 
 box to filter the Gantt chart before the planning objects are loaded. 
 Once selected, a Go button appears 
 in the top left corner of the Gantt chart. You need to select a filter 
 and then click Go before the Gantt 
 chart loads the planning objects based on the filter. Select the "Use Prefiltering" check 
 box to filter the Gantt chart before the planning objects are loaded. 
 Once selected, a Go button appears 
 in the top left corner of the Gantt chart. You need to select a filter 
 and then click Go before the Gantt 
 chart loads the planning objects based on the filter.
- Gantt Views I Want to Use: Select or clear the check box to display or hide the available Gantt 
 views. Select or clear the check box to display or hide the available Gantt 
 views.
- Full Grid View: Select this checkbox to display the Gantt Chart view as only 
 the Gantt table. The Gantt chart is not displayed. Select this checkbox to display the Gantt Chart view as only 
 the Gantt table. The Gantt chart is not displayed.
- Row Text Colors: Specify the row text color for activities you are responsible for or 
 for other activities that you are not responsible for. Click the color 
 box to the left of My Responsible Activities 
 or Other Activities to open the 
 color picker. Specify the row text color for activities you are responsible for or 
 for other activities that you are not responsible for. Click the color 
 box to the left of My Responsible Activities 
 or Other Activities to open the 
 color picker.
- Click OK.