Linking Planning Objects with the Edit Links Feature
Use the following procedure to add links with the Edit Links
feature.
To
use the Edit Links feature for Predecessor links
- Open the Gantt.
- Right-click
a task and select Edit Links.
- Click
the Predecessor tab.
- Click
New.
- Ensure
that [New]
is selected in the box below.
- In
the From
drop-down list, select the predecessor task.
- Select the link
type from the Link Type
drop-down list.
- If
necessary, enter a positive or negative value in the Lag field.
- Ensure
the Active box
is selected to indicate that this link is an active link.
- Click
OK.
To
use the Edit Links feature for Successor links
- Open
the Gantt.
- Right-click a task and select Edit
Links.
- Click the Successors
tab.
- Click
New.
- Ensure that [New] is selected in the box below.
- In the From drop-down list, select the successor task.
- Select
the link type in the Link Type
drop-down list.
- If necessary, enter a positive or negative value in the Lag field.
- Ensure the Active box is selected to indicate that this link is an active link.
- Click OK.