Open topic with left hand navigation
Linking Planning Objects in the Gantt Chart
Use the following steps to create links
in the Gantt chart.
To
link planning objects in the Gantt chart
- Open
the Gantt chart.
- Select the bar of the predecessor planning object until the cursor displays as a cross.
- Move
the cross to the bar for the successor task and click the left mouse button.
- The New Link
dialog box appears. Complete
the following information:
- Link Type: Select a link type.
- Lag: Optionally enter the number of days lag. To add a delay between the
start or finish of the tasks, enter a positive lag value. To show overlap,
enter a negative lag value.
- Click
Create.