Select from the following curves depending on what you want to display:
Current
Cost External: Select Current Cost External to display cost values for the current
schedule using the external cost rate or fixed cost values for Fixed Cost
assignments.
Current
Actual External: Select Current Cost External to display cost for the current schedule
using the external cost rate or fixed cost values for Fixed Cost assignments.
Current
Remaining External: Select Current Cost External to display remaining cost for the current
schedule using the external cost rate or fixed cost values for Fixed Cost
assignments.
Approved
Cost External: Select Approved Cost External to display cost values for the approved
schedule using the external cost rate or fixed cost values for Fixed Cost
assignments.
Approved
Actual External: Select Approved Actual External to display actual cost values for the
approved schedule using the External cost rate or fixed cost values for
Fixed Cost assignments.
Approved
Remaining External: Select Approved Remaining External to display remaining cost values
for the approved schedule using the External cost rate or fixed cost values
for Fixed Cost assignments.
Select Approved Schedule Variance External to display the variance,
calculated as:
Approved Cost -
(Actual Cost + Remaining Cost)
Baseline
Cost External: Select Baseline Cost External to display the cost values for the baseline
schedule using the external cost rate or fixed cost values for Fixed Cost
assignments.
Baseline
Actual External: Select Baseline Actual External to display actual cost for the baseline
schedule using the External cost rate or fixed cost values for Fixed Cost
assignments.
Baseline
Remaining External: Select Baseline Remaining External to display remaining cost for the
baseline schedule using the External cost rate or fixed cost values for
Fixed Cost assignments.