Open topic with left hand navigation
Chaining Multiple Tasks
Proliance provides enables you to create links between multiple
tasks by chaining these tasks together. When you chain tasks, Finish to
Start links are created between tasks in the order they appear in the
schedule. No lag is added to these links.
To
chain tasks together
- Open
the Gantt.
- Select
the tasks you want to link together.
- Select the Chain Tasks icon.
- Proliance
links the tasks in the order that they were selected and creates Finish
to Start links without lag".
To
unchain linked tasks
- Open
the Gantt.
- Select
the tasks you want to unchain together.
- Select
Unchain Tasks icon.
- Proliance
unchains the tasks that were linked together.